← All projectsMarlowe Quarter — Phase II
Ref. 88-4210 · Marlowe Estates LLP · Manchester, UK
Approved 24 Jan 2024 · Report cut 12 Mar 2025
Approved budget
£40.00M
Baseline · unchanged
Actual to date
£18.62M
46.6% consumed
Forecast at completion
£41.36M
+3.4% vs baseline
Committed not spent
£6.05M
POs · change orders
Budget vs. actual — drawdown
Approved budget £40.00M · Forecast £41.36MActual spentForecast overrun £1.36MToday £18.62M / £40.00M
Spend over time
Monthly spend · Cumulative